Commercial Property Pothole Repair And Asphalt Patching
This standard operating procedure covers the complete process for restoring distressed asphalt surfaces on commercial parking lots, loading bays, and access roads — from saw-cutting sound boundaries through final compaction and traffic reopening.
To provide a repeatable, quality-controlled method for repairing potholes and patching deteriorated asphalt on commercial properties. This procedure ensures structural integrity of the pavement, prevents water ingress and further subgrade failure, extends the service life of the surface, and minimizes liability from trip hazards and vehicle damage. Proper execution restores a smooth, free-draining surface that meets safety and appearance standards for tenant, customer, and delivery traffic.
This SOP applies to all commercial property asphalt surfaces including parking stalls, drive aisles, loading docks, and pedestrian walkways where the substrate remains structurally sound and the distress is limited to the wearing course. It covers hot mix and cold patch methods for patching areas up to 2 m² per repair. Full-depth reclamation, overlay construction, and crack sealing are outside the scope of this document.
- Lockout/Tagout any adjacent utility vaults, irrigation controllers, or electrical junction boxes that could be struck during saw-cutting or jackhammer operations. Confirm underground service locations before any excavation exceeds 100 mm depth.
- All personnel must wear CSA-approved high-visibility vest, steel-toed boots, cut-resistant gloves, safety glasses with side shields, and hearing protection (minimum NRR 25 dB) during saw-cutting, jackhammering, and compaction. Class 2 hard hat required when working within 3 m of overhead obstructions or equipment.
- Hot mix asphalt is delivered at 140–165 °C. Keep exposed skin clear of material and tools. Use insulated gloves and long sleeves when handling hot rakes or lutes. Burn protocol must be posted in the crew vehicle.
- Establish a temporary traffic control zone per the local jurisdiction's traffic management manual. Use cones, signage (ROAD WORK AHEAD, LANE CLOSED), and a flagger if vehicle speed exceeds 30 km/h or visibility is limited. Never leave an open excavation unattended without barricades.
- Hot mix asphalt (HMA) PG 58-28 or equivalent, delivered at 140–165 °C, OR cold patch asphalt (UPM or equivalent) for temporary repairs below 10 °C ambient
- Emulsified tack coat (SS-1h or CSS-1h) diluted 1:1 with clean potable water
- Asphalt saw (walk-behind or handheld) with diamond blade rated for asphalt — minimum blade diameter 300 mm
- Jackhammer with 50 mm (2 in) chisel bit or pneumatic breaker
- Square shovel (flat-blade), stiff-bristle push broom, and industrial vacuum or compressed air for debris removal
- Hand-pump sprayer or backpack sprayer (20 L capacity) dedicated for tack coat application
- Vibratory plate compactor — minimum centrifugal force 12 kN, or hand tamper for areas under 0.5 m²
- Asphalt rake (lute) — 900 mm wide with 1.8 m handle
- Measuring tape (8 m), straightedge (2.4 m), and string line for grade control
- Personal protective equipment as listed in Safety Precautions
- Traffic control kit: 10 traffic cones (900 mm), 4 signage stands, ROAD WORK AHEAD sign, LANE CLOSED sign, and flagger vest + paddle