First Article Inspection (FAI) and Quality Sign‑Off
This procedure defines the mandatory steps for performing a First Article Inspection (FAI) on initial production parts or after any significant process change. It ensures that all dimensional, material, and process requirements are verified and formally approved before full production release, reducing scrap, rework, and customer non‑conformances.
The purpose of this First Article Inspection (FAI) procedure is to establish a standardised method for verifying that the first produced part conforms to all engineering, material, and process specifications. A fully documented FAI provides objective evidence that the manufacturing process is capable of producing conforming parts, identifies potential issues before production ramps, and serves as a baseline for future process control. This procedure aligns with AS9102 / PPAP requirements for aerospace, automotive, and precision manufacturing environments.
This SOP applies to all first‑article parts produced in the machine shop, fabrication cell, or assembly line. It is mandatory:
- Before production release of any new part number.
- After any engineering change (ECN) that affects form, fit, or function.
- After a change in manufacturing process, tooling, or fixture design.
- After a machine relocation or major repair that may affect process capability.
- After a hiatus of more than one year for a given part number.
This procedure does not replace in‑process inspections or final quality audits; it is a discrete first‑article verification gate.
- Before handling the first article on a live machine, perform a lockout/tagout (LOTO) if any power source must be isolated for measurement access. Verify zero energy state.
- Wear required personal protective equipment: safety glasses with side shields, steel‑toe boots, and cut‑resistant gloves when handling sharp edges or burrs. Use gloves when cleaning surfaces with solvent.
- When using marking fluids, dyes, or solvents for non‑destructive testing, ensure adequate ventilation. Read SDS for each chemical. No open flames or smoking in the inspection area.
- For heavy first articles (>20 kg), use a hoist or lift assist. Never lift alone. Ensure the part is securely supported on the surface plate or measurement fixture.
- Approved part print / engineering drawing – current revision with sign‑off.
- FAI check sheet (AS9102 Form 1 or customer‑specific format).
- Calibrated micrometers (0–25 mm, 25–50 mm, etc.), digital calipers (150 mm / 300 mm), depth gage, and thread gages (GO/NO‑GO).
- CMM (Coordinate Measuring Machine) – program verified against master if used for complex geometries.
- Surface plate (Grade B or better), height stand, and dial indicator with 0.01 mm resolution.
- Material cert (mill test report) or supplier certificate of conformance.
- Process traveler / work instruction – current revision.
- Digital camera (at least 5 MP) for photographing interfaces and critical features.
- Marking pen (non‑transferable), inspection stamp, and red NCR flags.
- Solvent (isopropyl alcohol or approved cleaner) and lint‑free wipes.