Daily log for monitoring cooling tower water chemistry — conductivity, pH, TDS, biocide levels, and bleed-off cycles. Pass/fail thresholds are based on manufacturer specifications and ASHRAE Guideline 12-2020. Each row includes a blank for actual readings so operators can record data directly on the floor.

Frequency
Daily
Department
Maintenance / Water Treatment
Asset Type
Cooling Tower (all types)
Version
1.0
Free download — no sign‑up, no email.Take this log to your shop floor and mount it on a clipboard.
Overview & Purpose

This daily water treatment log is designed to verify that cooling tower chemistry stays within manufacturer‑specified limits for conductivity, pH, total dissolved solids (TDS), and biocide residual. Routine testing prevents scale deposition, corrosion, and microbiological fouling — extending equipment life and reducing unplanned downtime. Each inspection item includes a pass/fail checkbox and a blank for the actual reading. If a reading falls outside the tolerance band, the operator must document the issue in the Defect / Corrective Action Log below and initiate a work order.

Equipment & Safety Prerequisites
  • LOTOVerify lockout/tagout on the tower fan motor and chemical feed pump before accessing the basin. Confirm zero energy state.
  • PPEWear chemical‑rated gloves, safety glasses, and a faceshield when handling treatment chemicals and collecting water samples.
  • CALConductivity meter and pH probe must be field‑calibrated daily per manufacturer instructions. Record calibration at the bottom of this log.
  • MSDSReview SDS for all on‑site treatment chemicals (corrosion inhibitor, biocide, scale dispersant) before beginning the test sequence.

Inspection / Log Matrix — Cooling Tower Daily Water Chemistry

Status (P/F) Inspection Item / Task Tolerance / Threshold Actual Reading
[ ] Pass [ ] Fail Conductivity — record bulk water conductivity (µS/cm) 800 – 1200 µS/cm (adjust per tower manufacturer spec) _________ µS/cm
[ ] Pass [ ] Fail pH — record pH of basin water 7.2 – 8.4 pH units _________ pH
[ ] Pass [ ] Fail Total Dissolved Solids (TDS) — record TDS in ppm ≤ 1800 ppm (or 1.5× conductivity µS/cm conversion) _________ ppm
[ ] Pass [ ] Fail Bleed-off / blowdown operation — verify solenoid opens and flow is visible Bleed valve actuates at conductivity setpoint ±10 % ________ / setpoint
[ ] Pass [ ] Fail Corrosion coupon appearance — inspect weight‑loss coupon (if installed) No pitting, uniform colour, < 2.0 mils/year _______ mpy
[ ] Pass [ ] Fail Biocide residual — test for total chlorine or bromine 0.2 – 0.8 ppm total chlorine (or 1 – 3 ppm bromine) _________ ppm
[ ] Pass [ ] Fail Chemical feed pump operation — verify stroke rate and suction line Inhibitor feed at 50–100 % of target dose rate (mL/min) _________ mL/min
[ ] Pass [ ] Fail Water temperature — record basin water temperature ≤ 35 °C (95 °F) max per ASHRAE Guideline 12 _________ °C
[ ] Pass [ ] Fail Visible debris / oil sheen — inspect basin surface No visible oil, foam, or floating debris _________ (notes)
[ ] Pass [ ] Fail Make‑up meter reading — record totalizer value Daily make‑up volume within 5 % of expected evaporation + bleed _________ m³

Stop Chasing Maintenance Blindly

Track every calibration, pressure drop reading, and machine performance trend in one place. ServiceGrid logs your tasks automatically and alerts you before failure.

Try ServiceGrid →

Defect / Corrective Action Log

Date / Time Item # Issue Identified Corrective Action Taken WO #
___/___/_____ _______ _______________________________ _______________________________ _______
___/___/_____ _______ _______________________________ _______________________________ _______
___/___/_____ _______ _______________________________ _______________________________ _______
___/___/_____ _______ _______________________________ _______________________________ _______

If a pass/fail item in the matrix above is marked "Fail", the item number must be referenced in this log. Attach work order printout to the back of this sheet.

Sign-Off & Verification

By signing below, the inspector verifies that all water chemistry tests have been performed according to the manufacturer's specifications and facility water treatment protocol. Any out‑of‑range reading has been documented in the Defect / Corrective Action Log above.

Inspector Name / Signature
Date & Time
Equipment Calibration Check (conductivity meter / pH probe):
Standard value
As‑found reading
Tech initials

Software that works like your best tools.

This SOP library is maintained by Ryxen — focused software tools that solve specific operational friction points for Canadian small businesses. No ERP bloat, no per-user pricing, no demo calls.

SwitchDesk · Call Tracking SiteQueue · Install Tracking ServiceGrid · CMMS SupplyGrid · Material Orders SafeDesk · Safety Compliance ShopDocs · Visual SOPs